Project Update : August 2021

This summer has seen excellent progress on site, with the external brickwork now repaired and repointed, the restored parapet now almost complete and the interior ironwork cleaned and painted. Work on the tower will resume in mid September, with all the replacement stonework and other materials now on site.

Read More
Project Update : Rebuilding of the parapet - Phase 1 : the brick core

This update includes photographs of the tower and church interior where late Victorian floor tiles have been uncovered beneath a layer of concrete, and also a video tour with contractors explaining some of the proposed render finishes.

Read More
Project Update : Site Preparations

So exciting to see preparations underway by Coniston Ltd for start of works at Dockyard Church. Vegetation cleared, hoarding up, compound in place. Waiting for the serious work to begin on 2 November. Build duration will be 83 weeks with the Church re-opening in September 2022.

Read More